Using Sliding System of Bridge Girder Erection Machine to Implement Suspending and Setting of Small Box Girder at Joint of Ramp and Principal Line

Qin Ying-bin
Abstract:Combining with an actual engineering,it is introduced that the box girder is taken to its position through transverse sliding on bridge girder erection machine after the addition of sliding system.The practice indicates that the speed and quality of erecting and transporting beam under normal condition can be reached in using bridge girder erection machine to erect interchange through selecting equipments in reason and adopting necessary safety measures.
Engineering
What problem does this paper attempt to address?