Retrofitting of 75 t/h tower type circulating fiuidized bed combustion boiler

谭厚章,贺军全,刘继录,刘志强
DOI: https://doi.org/10.3969/j.issn.1004-9649.2003.08.018
2003-01-01
Abstract:The 75 t/h tower type circulating fluidized bed combustion (CFBC) boilers in Daliuta Cogeneration Power Plant couldn't take full load and serious wearing problems existed on the furnace heating surfaces before retrofitting. Through testing and analysis, the causes of these problems were found out. Through the retrofittings of forced draft fans, and the adjustment of primary air quantity and secondary air ratio, the CFBC boilers have been able to operate at full load and the wearing of heating surfaces have been greatly reduced.