An Experimental Study on the Performance of Storage Pulverizing System after Renovation of Importing Hot Air

Guoqing Han,Hongqi Wei,Chang-zheng He,Ying-hui Li
DOI: https://doi.org/10.4236/epe.2013.54b065
2013-01-01
Energy and Power Engineering
Abstract:A thermal power plant of Sinopec has 9 boilers, which generally have problems of high exhaust gas temperature and high flying ash carbon content.In order to improve the adaptability of coals, the stability of coal powder ignition, the burn-off rate of pulverized coals and the boiler efficiency, a series of renovation projects about importing hot air into mill exhauster are proposed.For the sake of verifying the renovation effects, an efficiency performance test is conducted on the renovated #5 boiler.The test result shows that the boiler heat efficiency has improved by 0.4% and it operates more safely and reliably after the renovation.At last, this paper recommends an optimized operation mode.