Study on Transient Overvoltage of Zhexi Converter Station of ±800 Kv DC Power Transmission Project

陈锡磊,周浩,王东举,沈扬,钱锋,周志超,丘文千
DOI: https://doi.org/10.13335/j.1000-3673.pst.2012.03.012
2012-01-01
Abstract:The transient overvltage and load of arresters in Zhexi converter statiom for ±800 kV DC power transmission project from Xiluodu to Zhexi are simulated and analyzed in details. To carry out this research, following fault conditions are chosen: three typical faults in AC system, i.e., three-phase ground fault of AC bus, interphase switching surge in AC system and losing AC power source, and three typical faults in DC system, i.e., single-phase ground fault occurred at upper rectifier bridge side of wye-wye connected winding of converter transformer, single-phase ground fault occurred at lower rectifier bridge side of wye-wye connected winding of converter transformer and full-voltage starting. Research results show that the losing AC power source is the most severe fault condition of AC system, under which the overvoltage of AC bus is 771 kV, the maximum current passing through arrester of AC bus is 0.14 kA and the maximum energy entering arrester is 2.07 MJ; when single-phase ground fault occurs at upper rectifier bridge side of wye-wye connected winding of converter transformer, the overvoltage cross the rectifier bridge is 375 kV, the maiximum current passing through the valve arrester is 2.32 kA and the maiximum energy entering the arrester is 6.73 MJ; when single-phase ground fault occurs at lower rectifier bridge side of wye-wye connected winding of converter transformer, the maximum current passing through the valve arrester is 1.04 kA and the maiximum energy entering arrester is 2.84 MJ; the overvoltage appears on DC polar bus caused by full-voltage starting, is 1 330 kV, the mamimum current passing through polar bus arrester is 0.56 kA and the maximum energy entering the arrester is 4.35 MJ.
What problem does this paper attempt to address?