The Study of the Construction Technology of a Long Tunnel with a Small Cross Section

ZHANG Chuan-mao,ZHANG Bao-zhong,WU Fei-zhou
DOI: https://doi.org/10.3969/j.issn.1006-3951.2010.03.040
2010-01-01
Abstract:The paper gives an introduction to the new trackless construction technology of successfully conveying aggregates by means of a long tunnel with a small cross section for construction of Xiangjiaba hydropower project and sums up its relevant key technical problems such as ventilation and smoke discharging.The paper especially makes a study of selection and combination of trackless mucking ways and mucking equipment from a long tunnel with a small cross section.