Construction Monitoring for PC Composite Box-girder Bridge with Corrugated Steel Webs

Xiang Weikang,Zheng Shangmin,Wan Shui
DOI: https://doi.org/10.3963/j.issn.1671-7570.2013.01.001
2013-01-01
Abstract:Taking the Chuhe bridge on the North-line of the Fourth Bridge of Nanjing Yangtze River as an example,through the simulation calculation of construction process of the whole bridge,the construction control of the similar type bridges was studied in accordance with the structural characteristics of prestressed concrete composite box-gider bridge with corrugated steel webs.And the main monitoring contents,monitoring calculation,monitoring methods and monitoring effects during the cantileveredly cast construction of the bridge are introduced in detail.