EXPERIMENTAL STUDY ON SETTLEMENT AND STABILITY OBSERVATION OF HIGH-FILL EMBANDMENT IN THE JINING-FENGZHEN SECTION OF THE FREEWAY 208

SU Yue-hong,DU Rui-feng,BAI Zhi-ping
DOI: https://doi.org/10.3969/j.issn.1009-3575.2007.04.035
2007-01-01
Abstract:The geological condition in the Jining-Fengzhen section of the Freeway 208 is described in the paper.And the purpose of layout of observational apparatus and significance of observation is presented through the long-term settlement observation in the high-fill embankment.Based on the hyperbolic method,the Matlab program is applied to analyze the long——term stability of all the high-fill observed embankment sections in the project.In light of China Freeway Code,the total and residual settlement is within the project requirement.