Unstressed Cable Length and Geometric Linear Control of Hybrid Girder Cable-Stayed Bridge with 1000 m Sale Span

Xie Mingzhi,Bu Yizhi,Wei Ran,Li Shaopeng
DOI: https://doi.org/10.3969/j.issn.1674-0696.2013.03.02
2013-01-01
Abstract:In the light of the mechanical behavior and the major problems in manufacture and erection phase of hybrid girder cable-stayed bridge with 1 000 m scale span during construction stage,the control methods of unstressed cable length and geometric profile were studied on the base of the geometry control method,according to the construction control of Edong Bridge with a main span of 926 m.Based on the studies mentioned above,unstressed constants were adjusted both in manufacture and erection stage.Besides,the control of unstressed cable length and geometric profile were converted to the control of tension amount and girder angle,which was to be in accordance with ideal profile and cable force.The proposed method was an efficient method with high precision for bridge construction control.With this method,undesirable influence caused by natural environment can be reduced,and some construction errors can be avoided as well.Construction experience indicates that the theoretical calculation is in well accordance with the field results,which proves that the method presented is pretty effective and reliable.
What problem does this paper attempt to address?