Status and Commissioning Plan of Korea-4GSR

Jaeyu LEE,Jaehyun KIM
DOI: https://doi.org/10.3938/phit.33.012
2024-05-31
Physics and High Technology
Abstract:Multipurpose Synchrotron Radiation Construction Project is in progress to construct 4th generation storage ring with a 800-m-long circumference in Ochang. Its beam parameter is 4 GeV electron beam energy, lower than 100 pm emittance, 100 mA beam current. Currently, Korea Basic Science Institute is in charge of construction and Pohang Accelerator Laboratory (PAL) is in charge of the accelerator complex and ten beamlines. Recently, PAL is finalizing technical design and producing prototypes. In this report we introduce status and commissioning plan of 4GSR project focusing on beam physics part.