Commissioning of RF system of the 200 MeV proton cyclotron

Chen,Guang Liu,Yanping Zhao,Zhen Peng,Xin Zhang,Chujie Chao,Xuyun Long,Chuansong Yu,Oleg Karamyshev,Galina Karamysheva,Grigori Shirkov,Antonio Caruso,Luciano Calabretta,Gen Chen
DOI: https://doi.org/10.1088/1742-6596/1350/1/012191
2019-11-01
Journal of Physics: Conference Series
Abstract:Abstract The SC200 superconducting accelerator which is designed for proton therapy is currently under construction. The RF (Radio Frequency) system has been designed and constructed as a subsystem of the SC200. To verify the stability of the RF system, a high-power feeding test was performed for the cavity. This paper mainly reports on the overview of RF systems and the preliminary high-power commissioning, as well as the problems found and improvements made during the commissioning process. The results show that the RF system has initially achieved the designed goal, and each loop (amplitude, tuning, phase) can work effectively. The cavity can operate in a ~50 kW continuous wave state. Next, the formal RF conditioning will be carried out after the complete assembly of cyclotron, so as to confirm the cavity can run smoothly under 80 kW, which is part of the whole commissioning process.
What problem does this paper attempt to address?