Construction technology of the freezing method for the connecting-passage in the subway

Mengheng Zhang,Heng Wan,Yongjie Yang,Yufei Mao,Wei Li,Peng Shen,Qingfei Luo
DOI: https://doi.org/10.1088/1755-1315/384/1/012090
2019-11-01
IOP Conference Series: Earth and Environmental Science
Abstract:Abstract Taking the subway shield tunnel of Dagengjia Station to Longchuan Road Station of the first phase of Harbin Rail Transit Line 2 as the background, the freezing construction scheme and construction of the interval connecting-passage were introduced. The analysis and monitoring data show that the maximum settlement of the ground caused by the construction of the freezing method is -5mm, the maximum ridge is 6.12mm; the maximum settlement of the underground pipeline is -5.51mm; the maximum settlement of the connecting-passage is -7.13mm, the convergence value The maximum is 1.80mm, which is less than the construction control value and meets the construction requirements.