TRIAXIAL MIXED PILE JOINT DEWATERING METHOD FOR CONSTRUCTION OF PASSAGE CONNECTING TUNNELS

YANG Yong-yong,SHI Wen-guang,ZHAO Yu,SHANG Yue-quan
DOI: https://doi.org/10.3969/j.issn.1000-4726.2012.03.003
2012-01-01
Abstract:The burial depth is shallow in the connecting passage of No.8 shield tunnel of Hangzhou subway line 1 and the surrounding earth is silty soil containing high moisture.Triaxial mixed pile joint dewatering construction method is adopted in consideration of the following points,such as conditions are available for road reinforcing,there is no important building near the construction site,dewatering conditions are available,and compared with freezing method,the ground reinforcing joint dewatering construction method may save cost without affecting the tunnel construction.Dewatering and other technical problems in construction are successfully solved and soil stabilization is ensured during construction of connecting passage.