Analysis of Measured Data of Connected Aisle in Metro Tunnels by Freezing Construction Method

Wang Zhiliang,Shen Linfang,Li Mingyu
DOI: https://doi.org/10.3969/j.issn.1673-0836.2010.01.026
2010-01-01
Abstract:The horizontal ground freezing method,soil excavation sequence,soil thaw and grouting of connected aisle were introduced within one subway construction using freezing method in Shanghai.The salty water temperature,frozen soil temperature,settlement of the ground surface,pressure in pressure released holes and deformation of the tunnel are measured during the constructing period.The results were analyzed and the changing rules of monitored data were obtained.In the end of the paper some suggestions were given in order to supply reference for construction of connected aisle in the future.