Calculation and Test of Sheath Overvoltage of Single-core Cable

GUO Xing-jun,NIU Hai-qing,WANG Xiao-bing,LIU Yi-gang,YI Ze-pei,ZHANG Yao
DOI: https://doi.org/10.3969/j.issn.1003-6520.2007.10.035
2007-01-01
Abstract:Based on the typical cable sheath grounding style on Guangzhou power grid and the cable connection style with power system,the ATP models of calculating switching overvoltage on cable sheath are set up,3 typical switching overvoltages of cable sheath under closing transmission line to power system,single phase grounded,and 3-phase load turned off,are simulated by the ATP-EMTP.To verify the correctness of models and calculation and analysis results,the authors performed several impact trials in the real cable line of Guangzhou power grid system.On the basis of simulation,analysis of parameter and model,and the impact tests,the authors put forward the principles of selection of cable protector.