Experimental study on arranging the navigation channel and flow pattern in the upstream of TGP dam

Xingkui Wang,Zhicong Chen,Guixian Wang,Guangqian Wang,RenShou Fu
1997-01-01
Abstract:For the condition of the Three Gorges project (TGP) has been operated for about thirty years, the separating dike which includes both the ship lock and the ship-lift is recommended as the optimum scheme in the technical design. The intake of ship lock located outside the dike is also suggested in this paper. Problems of the reciprocating flow, water stage fluctuation and the sediment deposition in navigation channel can be well solved in this scheme. A suggestion to raise the third-stage longitudinal cofferdam to elevation 148m will guide the water flow from the right side of the cofferdam to the right powerhouse. The experimental results indicate that it will greatly improve the flow pattern to guarantee the sluicing capacity of the outlet work and the power generation of the project.
What problem does this paper attempt to address?