Analysis on Experiment of Cathodic Protection for Underground Water Conveyance Pipeline

魏永庆,张立新
DOI: https://doi.org/10.3969/j.issn.1000-0860.2010.11.009
2010-01-01
Abstract:The length of the PCCP pipeline of the Water Conveyance Project of Dahuofang Reservoir(Phase II) is 154.4 km,and it is known from the investigation made on the soil and underground water environment of the region the pipeline passed through that the most part of the soil resistivity therein is between 20~50 Ω·m with a higher chlorine ion content in part of the region,which is a moderate corrosion environment,and then the difference of the cathodic protection design is larger as well.Therefore,an experiment on the cathodic protection is made before beginning of the whole construction project,so as to provide a scientific basis for the design of cathodic protection for the PCCP pipeline.