Research on excavation technology for pilot well of deep inclined shaft in high altitude and highland stressed area

ZHOU Feng,LIU Zhang,CHEN Gongmin,BAI Xianjun,SHI Kebin
2011-01-01
Abstract:The site of Bulunkou-Konggur hydropower station is located in an area with high terrestrial stress and high altitude.As one of the biggest steeply inclined shaft among the shafts which have been built and are being built,its inclined diversion shaft has many insecurity factors and construction difficulties.The construction scheme of first excavating the construction pilot shaft,then excavating from top to bottom was used in this project.The excavation method of construction pilot shaft with full face drilling blasting-bad rock displacement with gravity was used successfully through the technological innovation,which ensured the security,quality,progress and economy of construction pilot shaft and completed smoothly.