Design and monitoring of deep excavation with semi-top-down method in Hangzhou Jiebai commercial building

Hong-wei YING,Kui-hua WANG,Kang-he XIE,Qiu-yuan PAN,Zhong-lin Chen
DOI: https://doi.org/10.3321/j.issn:1000-4548.2001.01.019
2001-01-01
Abstract:A 14.7~15.2 m deep excavation in Hangzhou,with semi-top-down constructing method,is given as a case history.0.8m-thick diaphragm is used as the retaining wall,and partial structural beams and slabs of the basement are designed to constitute the strut system.Some useful conclusions are obtained through the analyses of the measured results.
What problem does this paper attempt to address?