Lightning protection renovation of 500 kV Yuan-an No.2 transmission line

Jidong Zeng,Shuiming Chen,LiChun Yang
2012-01-01
Abstract:The 500 kV Yuan-an No.2 transmission line, which belongs to Jibei Datong EHV Power Supply Corporation and was put into operation in April, 2003, passes through mountain area, so every year there are one to three times of lightning trip-outs occurred in the transmission line. To solve this problem, the lightning protection performance of this line is calculated and analyzed by Monte Carlo method, and comprehensive improvement measures for this line was proposed in 2006, including grounding grid renovation, installing sideward rods against shielding failure, installing line arresters and so on. The effectiveness of the proposed comprehensive improvement measures and the availability of Monte Carlo method are verified by actual running results of the improvement measures from 2007 to 2009.