Calculation of Sirocco Circulating on Tubular Air Pre-Heater and Leak Proof Measurement

范诚豪,韦红旗
DOI: https://doi.org/10.3969/j.issn.1672-9064.2008.06.017
2008-01-01
Abstract:NO.1 boiler economizer of Yangtze power plant wears severely. The paper introduces that the renovation of the economizer and air pre-heater during the period of maintenance in Yangtze Power Plant .Some relevant leak proof measurement are present. When the boiler flue gas temperature decrease, it will not cause serious low temperature corrosion by the environmental temperature decreasing. Through reasonable acid dew point and air pre-heater minimum wall temperature calculation and thermal calibration of recycling air volume, it presents that the installation of hot air recirculation are reasonable. It will be practicable value to operate safely of power plant's boiler.
What problem does this paper attempt to address?