Study of Cracking and Corresponding Treatment of Base Slab of Intake Tower in Hekoucun Reservoir

徐庆,黄达海,汪军,欧阳建树
DOI: https://doi.org/10.3969/j.issn.1000-1379.2016.04.029
2016-01-01
Abstract:In the project of Hekoucun Reservoir, numerical simulation using the finite element method was applied to the crack analysis on the upper base slab in the intake tower of No. 1 spillway tunnel, and the extended duration of concrete pouring as well as the large daily variation of the air temperature was also incorporated into the simulation analysis. The results indicate that the high top temperature should be largely responsible for the cracking of the upper base slab, and the extended duration of concrete pouring as well as the large daily variation of the air temperature may also induce the cracking in some degree.