Solution to Avoid Unreasonable Action of Remote Backup Protection under Post-fault Overload Condition

LIU Kun,CAO Runbin,DONG Xinzhou
DOI: https://doi.org/10.3969/j.issn.1007-290X.2015.07.016
2015-01-01
Abstract:Cascading trip caused by flow transferring is one of important factor to result in blackout. Therefore,aiming at problem of unreasonable action of zone-Ⅲ of distance protection under post-fault overload condition,research on wide area backup protection based on wide area measurement system information,overload restriction based on local information and overload identification and interlock based on domain sharing information was carried on. Schemes for solving this problem proposed at home and abroad were summarized,existing problems were analyzed and key problems to be studied and solved were pointed out.
What problem does this paper attempt to address?