Start-up and Hold-down Performance of a CFB Boiler with Water Cooled Square Cyclone

吕俊复,杨海瑞,郭庆杰,岳光溪,刘青
DOI: https://doi.org/10.3969/j.issn.1005-006x.2000.06.001
2000-01-01
Abstract:The start-up and hold-down performance of water cooled square cyclone CFB boiler is introduced with the object of a 75t/h capacity one in this paper. The total time from 0 to full load is about 1.5 to 2 hours, the average rate of temperature rise is 12℃/min, and max is 21℃/min. The temperature maintains about 6 to 7 hours to restart without burning oil, which spend 30 min or so. The total time for warm start-up is related with bed temperature, usually 30 to 60 min. The load changing rate range from 9%/min to 11%/min.