Activity Flow Optimization and Risk Evaluation of Complex Project

Chen Dong-yu,Qiu Wan-hua,Yang Min,Leung Mei-yung
DOI: https://doi.org/10.1109/wicom.2007.1272
2007-01-01
Abstract:In order to effectively control the schedule and cost of complex project, this paper proposes an algorithm for optimizing activity sequences and a model for evaluating schedule/cost risks based on Dependency Structural Matrix (DSM) theory. The activity optimization algorithm aims to reduce unnecessary activity rework by arranging activity execution order properly. Risk evaluation model also takes account of the uncertainties of project activities as well as learning effects. The simulation result indicates that our optimization algorithm can effectively reduce cost and compress schedule for complex projects.