Decomposition and Optimization Methods for Large-Scale Project Schedules

CHENG Xu,WU Cheng
DOI: https://doi.org/10.3321/j.issn:1000-0054.2009.01.040
2009-01-01
Abstract:Exact algorithms for large-scale resource constrained project schedules require excessive computing times while the solution quality of heuristics algorithms are not good enough.A project decomposition method with intelligent optimization was developed by combining serial and parallel decomposition methods.The optimization algorithm was the project coordination method based on sampling selection with sub-projects optimized by a bound algorithm.The effect of key parameters on the solution quality and time were analyzed for various simulated scenarios.The simulations show that the algorithm provides a better average quality of solutions than other heuristic algorithms.
What problem does this paper attempt to address?