Robust Optimization-Based Genetic Algorithm for Project Scheduling with Stochastic Activity Durations

Yongyi Shou,Wei Wang
2012-01-01
Abstract:The deterministic resource-constrained project scheduling problem has been widely studied. A key assumption in this basic problem is that the baseline schedule will be performed as planned. Since uncertainties prevail in the real world, a robust schedule is more valuable than an ideal but impractical schedule. A robust optimization model is established for project scheduling with stochastic activity durations to improve the schedule robustness. A robust optimization-based genetic algorithm is proposed to generate stable schedules which are insensitive to activity duration uncertainties. Various genetic operators and parameter values are tested on a large set of benchmark instances.