Discussions on optimizing methods of underground powerhouse

Ma Ji-ming,Xia Yu-li,Gu Zhao-qi
DOI: https://doi.org/10.3969/j.issn.0559-9342.2005.12.016
2005-01-01
Abstract:With the advanced rock excavation methods,underground powerhouses are widely used.So,it is necessary to optimize the design of underground powerhouse.The main aim of this paper is reducing the size of underground powerhouse.It includes many optimizing measures of underground powerhouse,which will be applied to Muzuo Hydroelectric station in Sichuan Province.And it explains how to apply these measures to design,by contrasting former with optimized.Moreover,it discusses three key problems involved in cables in the powerhouses crown,drainings around caverns and crane beams anchored at rock mass.
What problem does this paper attempt to address?