Operating practice of temperature and humidity independent control air conditioning system in an office building in Shenzhen

Yang Haibo,Liu Shuanqiang,Liu Xiaohua
DOI: https://doi.org/10.3969/j.issn.1002-8501.2009.05.031
2009-01-01
Abstract:Presents the operating and testing results of the system applied in this building,which show that the liquid desiccant fresh air handling unit can totally eliminate the space moisture load and the sensible load from the occupants and that the indoor temperature is about 25-26 ℃,the relative humidity is around 50%-60%,and the dry fan-coil unit can keep dry condition in the whole cooling period.In the project,the fresh air handling unit should be operated 1.5-2 hours in advance to eliminate the latent heat load and the high temperature water chiller should be operated 1-1.5 hours in advance to carry away the indoor sensible heat load.