Smelting Practice with Low Grade Iron Ore at 3200m~3 Blast Furnace of TISCO

YANG Xiao-dong,YAO Hong-xin,SUN Liang,LI Hong-fei
2013-01-01
Abstract:Aiming at the situation of iron ore grade declination for 3 200 m3 Blast Furnace of Tianjin Iron and Steel Group Company Limited (TISCO), the authors took measures such as enhancing management over charging raw material and fuel, optimizing burden structure, implementing foreman operation standardization system, adopting low silicon and low surfer smelting, maintaining rational actual blast flow rate and blowing kinetic energy and increasing top pressure. Consequently, long term stable, balanced and high efficient production was achieved at the blast furnace. The paper provides experience for smelting of large scale blast furnace with low grade iron ore.