Improved Hybrid Rescheduling Strategy for Semiconductor Manufacturing

QIAO Fei,LI Li,WANG Zun-tong,GUO Chun-zhong
DOI: https://doi.org/10.3969/j.issn.1006-5911.2007.03.023
2007-01-01
Computer Integrated Manufacturing Systems
Abstract:Semiconductor manufacturing oriented rescheduling strategy was focused,which was to determine when to start a rescheduling procedure as internal or/and external changes occurred.After comparisons among three existing rescheduling strategies: periodic strategy,event-driven strategy and hybrid strategy,an improved hybrid rescheduling strategy was proposed.There were two improvements upon the normal hybrid strategy,one was the influences on rescheduling strategy exerted by several rescheduling factors,another was to introduce minimum interval constraint between two rescheduling points so as to balance the sensibility and stability.Finally,an example was provided to show that the proposed rescheduling strategy could achieve better rescheduling result with lower computational cost.