Simulation-based rescheduling strategy of tank farm operations in refinery

WANG Zihao,RONG Gang,FENG Yiping
DOI: https://doi.org/10.3969/j.issn.0438-1157.2012.09.013
2012-01-01
Abstract:To enhance the robustness of the scheduling in refinery with operational uncertainty,a novel rescheduling method based on a two-level simulation system is proposed in this paper.The lower level model with uncertainty in the tank farm is used to simulate the deviation from the original plan.And the heuristic rule is further applied to the upper level simulation model according to the disruptions from the lower level to get the conservative plan which satisfies both material and components constrains simultaneously.Subsequently,by fixing the value of binary decision variables and penalizing the simulated deviation in the MILP model,a sub-optimal solution is obtained with less computational effort.The effectiveness of the proposed rescheduling framework is illustrated through a tank farm operation case in real world refinery.