A Study on Critical Chain Project Network Scheduling Technology under Double Constraints

李俊亭,王润孝,杨云涛
DOI: https://doi.org/10.3969/j.issn.1007-5429.2010.03.014
2010-01-01
Abstract:Based on CCPM methodology—drum resource conflict prior scheduling rules,the paper proposes critical chain project network representation method with FS representing for precedence relations-constraint and SS representing for resource-constraint.The method improves the traditional CPM/PERT technology which only considering precedence relations between activities.Further more,a principle method for identifying the key activities and critical path in network based on resource free float concept is presented.