Identifying Critical Activities In Multiple Projects

Yy Shou
2005-01-01
Abstract:The critical path method provides a sequence of critical activities according to time-only analysis. The critical chain method goes further and provides a chain of critical activities according to both time and resource analysis. However, for multiple simultaneous projects, the criticality of activities may vary due to complex resource dependencies. Defining critical activities in multiple projects as those whose delay with postpone one or more projects, a procedure is suggested to estimate resource-constrained floats associated with project activities and hence to identify critical activities. The proposed procedure can be helpful for managing simultaneous large-scale projects with limited resources.