Simple $k$-crashing Plan with a Good Approximation Ratio

Ruixi Luo,Kai Jin,Zelin Ye
2024-04-16
Abstract:In project management, a project is typically described as an activity-on-edge network (AOE network), where each activity / job is represented as an edge of some network $N$ (which is a DAG). Some jobs must be finished before others can be started, as described by the topology structure of $N$. It is known that job $j_i$ in normal speed would require $b_i$ days to be finished after it is started. Given the network $N$ with the associated edge lengths $b_1,\ldots,b_m$, the duration of the project is determined, which equals the length of the critical path (namely, the longest path) of $N$.