Abstract:Magnet power supplies in the PSI accelerator complex with their control and field-bus are old. Some components are more then 30 years old. To guarantee further maintenance and to meet the more demanding specifications for operation with the 2mA beam, they have to be replaced. The switched power supplies, developed for SLS, will be used. This implies a major redesign of part of the accelerator control system, which is now based on CAMAC, ROAD-C and other in house developed hardware including the machine protection system. The modified control for the new set-up will be based on VME and alternatively CAMAC, with dedicated processors for the functionality of the machine protection system.
Accelerator Physics
What problem does this paper attempt to address?
The problem that this paper attempts to solve is: In the cyclotron facility at the Paul Scherrer Institute (PSI) in Switzerland, the magnet power supplies, their control systems and field buses can no longer meet the current operational requirements due to their long service life (some components are over 30 years old), especially in terms of stability, ripple and power - grid suppression when handling 2 mA beam currents. To ensure the continuous maintenance of the system and meet more stringent operating specifications, these old - aged devices must be replaced and upgraded. ### Main problem summary: 1. **Aged devices**: The existing magnet power supplies, their control and field - bus systems have become obsolete, with some components over 30 years old and difficult to maintain further. 2. **Insufficient performance**: The stability and ripple control of the existing system no longer meet the requirements for 2 mA beam - current operations. 3. **Outdated technology**: The old system is based on obsolete technologies such as CAMAC and ROAD - C, lacking the flexibility and reliability of modern systems. 4. **Unavailable hardware**: Some front - end processors and other key components have been discontinued and cannot be supported or replaced. 5. **Communication bandwidth limitation**: The serial CAMAC communication bandwidth is insufficient, affecting the performance of certain applications. ### Solution overview: - **Power - supply replacement**: Adopt the switching power supplies developed for SLS to improve performance and reliability. - **Control - system upgrade**: Introduce a VME and CAMAC hybrid architecture, gradually replace the old CAMAC system, and add new VME I/O modules. - **New - interface design**: Develop new intelligent - interface modules equipped with dedicated CPUs to replace the old "KOMBI" controllers and part of the interlock logic. - **Network enhancement**: Extend Ethernet to key locations, use 100 Mbps fiber - optic links (upgradable to 1 Gbps and above), and add front - end devices to support VME I/O. - **Interlock improvement**: The new interlock modules will provide more refined event - diagnosis functions, including pre - trigger and post - trigger analysis. Through these measures, PSI aims to upgrade its control system to the modern technological level, ensure that its accelerator facility can continue to operate efficiently and reliably, and provide technical support for future projects (such as PROSCAN).