Maintenance Duration Estimate for a DEMO Fusion Power Plant, based on the EFDA WP12 pre-conceptual studies

O. Crofts,J. Harman
DOI: https://doi.org/10.48550/arXiv.1412.4008
2014-12-12
Instrumentation and Detectors
Abstract:The erosion and high neutron flux in a fusion power plant results in the need for frequent remote replacement of the plasma facing components. This is a complex and time consuming remote handling operation and its duration directly affects the availability and therefore the commercial viability of the power plant. A tool is needed to allow the maintenance duration to be determined so that developments in component design can be assessed in terms of their effect on the maintenance duration. This allows the correct balance to be drawn between component cost and performance on the one hand and the remote handling cost and plant availability on the other.
What problem does this paper attempt to address?