A better understanding of tunnel deformable supports: from analytical model to engineering application
Kui Wu,Yuzhu Wang,Xiaomeng Zheng,Nannan Zhao
DOI: https://doi.org/10.1007/s43452-024-00929-2
IF: 4.042
2024-04-11
Archives of Civil and Mechanical Engineering
Abstract:The severe failure of strong supports occurred in the Xinhua tunnel that was a deep-buried tunnel excavated in squeezing ground. In order to address such problem, this study explores the possibility of applying deformable supports in this tunnel. The mechanical response of a circular "rockbolt and yielding lining" supported tunnel is studied from the perspective of the convergence-confinement method. The equations for calculating the elastic modulus, cohesion, and internal friction angle of bolted rock are provided firstly; the mechanical model of the bolted tunnel is established then, where the surrounding rock can be classified into the plastic bolted, elastic bolted, and elastic unbolted regions. The equations for constructing the ground reaction curve are provided considering rockbolt reinforcement and rock shear dilatancy. The reduced case that the surrounding rock does not generate the plastic region is discussed as well, if the support pressure is higher than the critical value. The required minimum support pressure is further determined following the assumptions of maximizing the utilization of rockbolt bearing capacity and generating no loosening rock pressure. The exact equations for determining the lining thickness and length of highly deformable elements are provided with the intention to ensure lining safety and accept rock displacement. Based on the consideration of shotcrete hardening property, the equation to calculate the yielding stress of highly deformable elements is provided. The equations for GRC in this study can be reduced to those without considering rockbolt reinforcement or rock shear dilatancy. The design model of yielding lining is well applied in the Xinhua tunnel. The analysis results show that the rock displaces for 382.6 mm and the lining generates a plastic displacement of 281.8 mm in the Xinhua tunnel using the strong supports, which have a good agreement with the field monitoring data. The required lining thickness is equal to 28 cm and the installation number and length of highly deformable elements are 9 and 41.3 cm, respectively, when the yielding lining is employed in the Xinhua tunnel. Finally, a parametric investigation is carried out, including the cohesion and internal friction angle of rock, rockbolt length, and initial ground stress. Some recommendations for the tunnel design are proposed.
engineering, mechanical,materials science, multidisciplinary, civil