NEW PROCESS IN CONSTRUCTION OF PRESTRESSED CONCRETE FRAME STRUCTURE OF MULTISAYER LARGE-AREA PLANT BUILDING

Yang Zongfang
Abstract:Plant building B and C in Changqing International Industrial Park of Zhongshan City have 3 stories each,totally covering an area of 84m×117m.Column grid is 12m×9m,and no expansion joint is set.Two-way bonded prestressed concrete frame structural system is adopted,and secondary beam of prestress with-out bond is adopted transversely.It is proposed that transverse latter-poured belt shall be canceled,two pieces of short-term latter-poured belts shall be set vertically and shall be constructed in three successive sections,and carborundum floor and structural concrete shall be formed once.In this way,waiting time of latter-poured belt can be shortened,and construction schedule can be quickened;In addition,no short prestressed tendon is set at latter-poured belt,which can reduce construction cost.