Mechanical evaluation analysis of pipe-liner composite structure before and after polymer grouting rehabilitation
Kangjian Yang,Hongyuan Fang,Xijun Zhang,Xueming Du,Bin Li,Kejie Zhai
DOI: https://doi.org/10.1016/j.engfailanal.2024.108050
IF: 4
2024-04-01
Engineering Failure Analysis
Abstract:In practical engineering, voids can still be present in pipelines even after cured-in-place pipe (CIPP) rehabilitation, which requires polymer grouting for repair. However, the effectiveness of polymer grouting is uncertain. To solve this engineering problem, a series of full-scale tests were conducted to analyze the mechanical differences of the pipe-liner structure before and after polymer grouting. Subsequently, a three-dimensional numerical model was established to supplement the limited full-scale test data, and the evaluation indices of mechanical properties of pipe joints, such as shear displacement, relative rotation, and bending moment, were analyzed. Finally, 20 sets of comparison experiments (containing different loading and voiding cases) were designed and statistically analyzed to evaluate the repair effect of polymer grouting. The results show that polymer grouting has a significant impact on the mechanical properties of the pipe-liner structure, effectively preventing accidents such as gasket fall off and pipe disconnections by reducing the shear displacement and relative rotation of the pipe by 39.4 % and 43.6 %, respectively. Polymer grouting can change the stress state of the pipe, with the average bending moments at the crown and springline of the pipe and the bending moment of the CIPP liner decreasing by 21.2 %, 12.0 % and 83.7 %, respectively, while increasing by 75.4 % at the invert of the pipe after the polymer grouting. When voids around the pipeline are found in practical engineering, polymer grouting should be used in a timely manner for repair.
engineering, mechanical,materials science, characterization & testing