Make-or-break during production: shedding light on change-orders, rework and contractors margin in construction

Peter E. D. Love,Lavagnon A. Ika,Dominic D. Ahiaga-Dagbui,Giorgio Locatelli,Michael C. P. Sing
DOI: https://doi.org/10.1080/09537287.2018.1535675
2019-01-29
Abstract:A considerable amount of research has examined the cost performance of construction projects, yet there has been a paucity of studies that have examined the impact that client initiated change-orders and rework have on contractors. This paper seeks to add further clarity to this issue by replicating previous empirically-based research to establish the validity and reliability of the key issues influencing a contractor's cost performance. A total of 98 projects were used to examine the value of rework and change-orders and their influence on a contractor's margin. Only 65% of projects experienced a cost increase, though a mean rework cost of 0.39% of the contracted value was incurred. The difference between approved client change-orders and those by the contractor for subcontractors was 0.5% of the total costs incurred, which adversely impacted the organisation's profit. Margin losses may well have been higher as rework is seldom formally documented and reported.
operations research & management science,engineering, industrial, manufacturing
What problem does this paper attempt to address?