Application of non-equal interval GM (1,1) model in prediction of building settlement

Jiameng Wei,Huagen Jiang,Jianpeng Diao
DOI: https://doi.org/10.1088/1755-1315/636/1/012023
2021-01-01
IOP Conference Series: Earth and Environmental Science
Abstract:Abstract In order to solve the impact of the uneven settlement of the building on the construction process and safety evaluation of the building, this paper takes the building settlement as the monitoring object, and uses the non-equidistant GM (1, 1) model to construct the model, and applies it to the construction of a building. Settlement analysis. In addition, the prediction accuracy of the model is tested for the posterior error ratio and small probability error to ensure the reliability and accuracy of the model application.
What problem does this paper attempt to address?