Numerical Simulation of Water Inrush in Thick Quaternary Slope

Guo Xianzhang,Tang Chun'an,Feng Qingbo,Zhang Juanxia
2012-01-01
Disaster Advances
Abstract:Iron Mine is one of the open pit mine with a designed yield of 15 million ton raw-ore per year. For the mine, near rivers, covered by a thick and large area Quaternary sediment (Qel) and with a final depth of more than 500 meters, it would truly be built a huge quaternary- sediment side slope under a complex hydrogeology condition. While excavating, though a grouting curtain had been built between the bank of river and the east side of the open pit slope, there still had water inrush occurred inside the slope. In this study, the numerical test was used to analyze the cause of the water inrush; it can be found that the numerical test results had a good agreement with the practice on site.