Multi-Mode Resource-Constrained Time/Cost Trade-off Project Scheduling Problem with Discounted Cash Flow
ZHANG Jing-wen,XU Yu,HE Zheng-wen
DOI: https://doi.org/10.3969/j.issn.1001-4098.2005.05.004
IF: 2.034
2005-01-01
Systems Engineering
Abstract:Abstrcat There are several limitations existing in the current research on discrete time/cost trade-offs project scheduling problems, for example, the resource capacity and the indirect cost are ignored, this situation is not correctly reflect the (projects') execution in practice. Therefore, A more realistic model is presented in this paper, which is the Multi-mode (Resource-constrained) Time/Cost trade-off project scheduling problems(MRCTCTPDF, for short), it takes the NPV as the objective function, and considering each item capital, such as the projects' indirect cost, the owner's payment, the bonus/penalty and the activity cost, moreover, the activities' cost is distinguished two parts: one is the constant, the other is the variable. We build the mathematic model about the MRCTCTPDF , then validate it by adopting an numerical example. The results shows that the optimal scheduling more closely related to the owner's payment and the resource constraint, it is very instructive for contractors to make decision to the projects' duration-cost trade-offs.