Status of ECRH project on EAST Tokamak

xiaojie wang,fukun liu,jiafang shan,handong xu,dajun wu,bo li,jiang zhang,yiyun huang,yunying tang,weiye xu,huaichuan hu,jian wang,li xu,wei wei
DOI: https://doi.org/10.1063/1.4864607
2014-01-01
AIP Conference Proceedings
Abstract:A 140GHz electron cyclotron resonance heating and current drive (EC H&CD) project for EAST Tokamak is launched in 2011 with a total power of 4MW and pulse length of 100 s. The main objectives of the system are to provide central H&CD, assist start-up and control of MED activities. The system comprises four gyrotrons each with nominal output power of 1MW at 140GHz. The RF power, transmitted through four evacuated corrugated waveguides will be injected into plasma from the low field side (radial port). The front steering equatorial launcher directs the RF beam over +/- 25 degrees toroidally and scans over 38 degrees poloidally. At present, the construction of the first 1MW system is undergoing for the expected campaign in the end of 2013. In this paper, the current status of the development and the design of the 140-GHz ECRH system are presented.
What problem does this paper attempt to address?