Abstract:Based on dynamic program an optimal model was proposed for load dispatch of the Turbo-generator sets. The restricted conditions of the model are considered, which include the service of main metal parts in the steam turbine due to low cycle fatigue, minimum startup and shutdown interval, increasing and decreasing of load rate as well as the other relative cost of the power plant. The factors, which affect load dispatching among units, were calculated and analyzed. A calculation example with 4×300MW units was given,in which the varieties of cost are converted into standard coal consumption of the power plant. The calculation results show that the optimum model can decrease the coal consumption by 3g/kW ·h when the electric power demands are satisfied.