Commissioning of HTR-10 before Fueling

苏庆善,王瑞偏,陈华,胡守印,梁锡华,孙栓樑
DOI: https://doi.org/10.3969/j.issn.0258-0926.2001.06.016
2001-01-01
Abstract:The commissioning of 10MW high temperature gas cooled reactor (HTR-10) is divided into 3 stages and includes 100 test items. This paper introduces systems of HTR-10 and principle of test items planning, especially introduces contents and results of some main test before first fueling, and nonconformity handling. Through these, tests components and systems are verified to meet the performance criteria.