Fluid-Structure Coupling Analysis of Dewatering and Excavation in 500kV Shanghai Expo Underground Substation

LIU Jing,CHEN Jin-jian,WANG Jian-hua
DOI: https://doi.org/10.16183/j.cnki.jsjtu.2010.06.001
2010-01-01
Abstract:On the background of 500 kV Shanghai Expo underground substation,a fluid-structure coupling FEM analysis of dewatering and excavation was made based on the Biot's consolidation theory.A pumping test was simulated to determine soil parameters by back-analysis of displacement and pore pressure.A fluid-structure coupling model was built to analyze dewatering and excavation with steady analysis method and birth-death element method respectively.Seepage and stress fields were solved at the same time.With comparison of the calculated and measured values,the fluid-structure coupling method used in the analysis of dewatering and excavation was proved to be correct and feasible.
What problem does this paper attempt to address?