Time Effect of Excavation Considering the Coupling of Seepage Flow and Soil Deformation

谢康和,李玉岐,周健
DOI: https://doi.org/10.3321/j.issn:0559-9350.2006.06.009
2006-01-01
Abstract:Based on Blot's consolidation theory,the finite element equation of 3-D consolidation considering unloading and water head difference between inside and outside of the foundation pit is deduced and the corresponding computational program for FEM is developed,by which the coupled effect of seepage flow and soil deformation can be analyzed.The time effects of foundation pit deformation,excess pore pressure and soil water potential are investigated.The comparison of calculation results show that the horizontal displacement of retaining structure,the ground surface settlement as well as the pit base heave all will be bigger if the water head difference is taken into account.
What problem does this paper attempt to address?