Design and Construction of Water Supply Pipeline Crossing River Project with Horizontal Directional Drilling Technology

CHEN Mu-min,TAN Jun-hong,LV Yue-jin,ZHANG Chun-hua,ZHANG Hui-guo
DOI: https://doi.org/10.3321/j.issn:1000-4602.2008.16.028
2008-01-01
Abstract:The water supply pipeline beside the Kaiping Bridge passes crossing the main channel of Tanjiang River.The pipeline is DN 800 PE,and the total length is 594.8 m.In order to ensure an unimpeded water way and protect the beautiful landscape along the river,it was determined that horizontal directional drilling technology was used to avoid the traffic control and damage to existing municipal facilities caused by excavation construction.The project has safe construction,short construction period and low cost,providing reference for construction of similar engineering.
What problem does this paper attempt to address?