Numerical Simulation on the Response of Adjacent Underground Pipelines to Super Shallow Buried Large Span Double-Arch Tunnel Excavation
Jianxiu Wang,Ansheng Cao,Zhao Wu,Zhipeng Sun,Xiao Lin,Lei Sun,Xiaotian Liu,Huboqiang Li,Yuanwei Sun
DOI: https://doi.org/10.3390/app12020621
2022-01-10
Applied Sciences
Abstract:The excavation of a shallow buried tunnel may cause stress redistribution in surrounding rock, and cause deformation, damage, and even destruction of adjacent underground pipelines. The land part of the Haicang undersea tunnel in Xiamen of China was a super shallow buried large span double-arch tunnel. Its construction was restricted by both underground excavation safe and adjacent pipeline protection. Multiple groups of working conditions were designed considering the relative position of pipe and tunnel, pipeline and tunnel construction parameters. Numerical simulation was used to study the influence of pipeline horizontal distance, buried depth, pipeline diameter, pipeline wall thickness, pipeline shape, pipeline material and excavation method on the response of adjacent underground pipelines. The results show that the relative position of pipe and tunnel, and the construction method of the double-arch tunnel have a great influence on pipeline deformation. Pipeline material, pipeline diameter and excavation method have a great influence on pipeline stress. The construction method was the key factor affecting the stress and deformation of the pipeline. The three-step reserved core soil method can effectively control the stress and deformation of underground pipelines. The research results can provide a reference for similar projects.